General Permitting Information

Updated 03/01/2025

View general permitting instructions.

Types of Permits

The Air District's permitting process encompasses multiple permit types to ensure comprehensive environmental compliance. While most projects require two fundamental permits, certain major facilities are subject to additional regulatory oversight.

The standard permitting process requires two critical permits that must be obtained prior to initiating any project. The two essential permits are the Authority to Construct (ATC) and the Permit to Operate (PO).

Authority to Construct Permit

The Authority to Construct (ATC) is the initial permit that evaluates and approves the proposed project's design and environmental specifications. This permit ensure that the planned facility meets all applicable air quality regulations before construction begins. Applicants must demonstrate compliance with all regulations and provide detailed project plans for review.  

Permit to Operate 

Following successful construction, the Permit to Operate (PO) becomes the final regulatory requirement. This permit validates that the completed facility operates in full compliance with established standards and emissions regulations. 

Title V Permits

For major stationary sources with significant emissions, Title V permits represent comprehensive operating permits which consolidate all air quality requirements for large-scale facilitates. Title V permits may impose more stringent monitoring, recordkeeping, and reporting obligations. 

Unlike standard ATC and PO permits, Title V permits apply to facilities that emit significant quantities of regulated pollutants.  

Permit Requirements

By law, an air quality permit is required for several scenarios which include:

  • Installing equipment that may cause air pollution
  • Modifying existing permitted equipment
  • Moving permitted equipment to a new location
  • Installing emission control equipment 

Permit Process

An Air District permit is a document that gives the permit holder authorization to build equipment and/or to operate that equipment. Nearly all stationary equipment that emits to the atmosphere requires an Air District permit. Each project is evaluated before a business can build and operate their equipment to ensure that all air quality requirements are met. During the permitting process, air quality engineers review projects, calculate emissions and determine compliance with all federal, state and local regulations before issuing a permit.

  • I. Application Received
    Step One
    Air District reviews application and contacts applicant
     
  • Step One
    1. Calculate Emissions and Conduct Plant Visit
    2. Complete a Health Risk Assessment
    3. Determine Compliance with Rules and Regulations
    4. Require Add-on Pollution Control Equipment
    5. Set Emissions & Operating Limits and Require Monitoring in the Permit Conditions
    6. Post a Public Notice, Address and Respond to All Comments
     
  • II. Issue Authority to Construct
    Step One
    Issue Authority to Construct After Review and Approval
     
  • Step One
    1. Project Construction, Startup, and Source Test
    2. Review Source Test for Compliance with Permit Conditions
     
  • III. Issue Permit to Operate
    Step One
    If All Requirements are Met, Air District Issues Permit to Operate
     
  • IV. Ensure Continued Compliance
    Step One
    Ensure Continued Compliance with the Enforcement Division

Contacting Us

Have a specific inquiry? Please use the appropriate contact method:

Open Burn Inquiries:

Asbestos, Demolition, Renovation, or Job Number Questions:

Facility with Assigned Engineering Staff:

  • Email your assigned staff member. For contact information, refer to the staff directory.

General Questions on Permitting or No Assigned Staff:

Questions on Compliance Assistance:

Contact Us

Asbestos
Asbesto

415 749-4762 asbestosjobs@baaqmd.gov


Información general de ingeniería

415.749.4990 permits@baaqmd.gov

Cumplimiento y Ejecución
Underground Tanks

415 749.4999

Contact Us

Spare the Air Status

Last Updated: 03/01/2025